Most deep-mining machines run on the camp's electric network. Learn how it works once and you will not get stuck with a dead machine.
The camp generator
Open the workshop and go to the Site tab for the Generator. It is a silenced diesel generator in the camp. You upgrade it in levels:
| Level | Capacity | Price | Company level |
|---|---|---|---|
| 1 | 20 kVA | $2,500 | 2 |
| 2 | 60 kVA | $7,000 | 3 |
| 3 | 150 kVA | $16,000 | 5 |
| 4 | 400 kVA | $38,000 | 7 |
| 5 | 1,000 kVA (a grid connection) | $90,000 | 9 |
The capacity is the total load the network can carry, counted against the machines' kW. The cage hoist needs at least the 60 kVA generator, and the big deep machines (jumbo, TBM, roadheader) want the 150 kVA one or more.
Extra generators
Once you have the 150 kVA generator, you can buy an Extra generator for $20,000. It adds 150 kVA to the network. You can have up to three.
Poles and the 30 m rule
Power travels by poles. Build a pole from build mode (B → Power & light → pole, $150). A pole must be within 30 m of the generator or of another live pole. Poles chain from the generator out into the field.
A machine or light runs if its power point is within 30 m of a live pole or the generator. If it is farther, it shows "no power" and the placement hint tells you the distance to the nearest live pole.

A few machines use a trailing cable instead of a plain 30 m rule:
| Machine | Cable reach from the nearest live pole |
|---|---|
| Drill jumbo | 60 m |
| TBM | 60 m |
| Roadheader | 100 m |
What things draw
| Consumer | Power |
|---|---|
| Floodlight mast (two LED floods) | 1.5 kW |
| Conveyor belt head | 15 kW |
| Water pump | 4 kW |
| Fan | 5.5 kW |
| Cooling unit | 15 kW |
| Headframe winder (while hoisting) | 45 kW |
| Auto-digger | 30 kW |
| Crusher | 22 kW |
| Sorter | 7.5 kW |
| Smelter | 5.5 kW coal, 75 kW electric |
| Dump station | 11 kW |
| Bridge conveyor | 7.5 kW |
| Drill jumbo | 55 kW while drilling |
| Roadheader | 90 kW cutting, 30 kW walking |
| TBM | 110 kW |
A winder that is standing still draws only a tenth of its rating.
When you place something, the build hint tells you how much it adds and warns you in red if it will overload the generator.
When the fuse trips
The network adds up the loads. If the total goes above the generator's capacity, the breaker trips and everything on the network stops: lights, conveyors, machines. A toast gives the load and the capacity and names the biggest consumer.

To get back on:
- turn something off or take it down,
- or buy the next generator level or an extra generator.
A machine that is about to start but would overload the network will refuse with "Generator too weak: N kW free, the machine needs M kW".
Lights
Headlamp and lanterns
Your helmet lamp is on with L. Lanterns and flares are hand items, useful in small spaces but not bright.
Floodlight mast
Build a Floodlight mast ($450) from the Power & light page. It has two LED floodlights and draws 1.5 kW. It lights up a large area at night: good for pits, yards and big rooms. It needs a live pole.

LED strip
Buy LED strip at the workshop (10 m for $80). Use it from your inventory or with B → Power & light. Hold the left mouse button and drag along a wall, a roof or the floor. The strip follows the surface. Click the right mouse button to pin a corner. Release to build. A single run can be up to 40 m. The metres you use come out of your stack and come back if you take the strip down.
A strip draws 12 W a metre. It is much brighter than a lantern, and a good way to light a drift all the way down.
Spotlight
The Spotlight is a 400 W LED floodlight ($180). Mount it on a wall, roof, floor or a machine, and aim it with your look. Use the mouse wheel, R and F to fine-tune. Later you can re-aim it with E. Its beam reaches 40 m.
Strips and spotlights need to be within 30 m of a live pole or a running generator.
Portable generator
A Portable generator costs $1,200. It is a diesel set with a 30 L tank that puts out 6 kW. Set it up on level ground from B → Power & light (it comes as a kit). Press E to start and stop it, F to refuel. It powers LED strips and spotlights within 30 m of it. It has no gas or exhaust risk, so it is safe anywhere, including deep in a dead-end drift. If you put too many lights on it, the newest ones turn off.
It does not power machines, only strips and spotlights.
Tips
- Put in poles first, before the machines. A line of poles to the working face costs little and saves trouble.
- Keep a small spare in capacity: a TBM alone draws 110 kW.
- Underground, a portable generator and a run of strip lights is the cheapest way to light a long dead-end drift.
- If a machine will not move and the prompt says "no power", the answer is nearly always one more pole.
- See Underground fleet for the LHD and mine truck, which run on diesel, not on the network.